Construction of a reinforced concrete structure at Skopje City Tower – a 60-meter high-rise distinguished by modern design and high-quality construction. This project is noteworthy for its swift execution, with just 9 days required to complete a 1,300m2 slab! The achievement was facilitated by utilizing the Faresin system for formwork on columns, beams, and slabs, complemented by the support of two cranes.
CLIENT | Balfin |
---|---|
LOCATION | Karpos, Skopje |
TOTAL AREA | 20.000 m2 |
YEAR | 2012 |